At the time of booking |
15% |
Within 30 days of allotment (by the banker) |
75% |
At the time of possession |
10% |
At the time of booking |
10% |
Within 45 days of booking |
75% |
At the time of possession |
5% |
At the time of booking |
10% |
Within 60 days of booking |
10% |
On commencement of excavation work |
10% |
On completion of DPC |
10% |
On casting of ground floor root slab |
10% |
On casting of first floor roof slab |
10% |
On casting of mumty/roof slab |
10% |
On completion of GI/CI piping |
5% |
On completion of electric conducting |
5% |
On fixing of doors/window frames |
5% |
On completion of plastering |
5% |
On completion of flooring |
5% |
At the time of possession |
5% |